LinkedIn Microsoft Project Skill Assessment Answer

In this article, you will find LinkedIn Microsoft Project Skill Answer, Use “Ctrl+F” To Find Any Questions or Answers. For Mobile Users, You Just Need To Click On Three dots In Your Browser & You Will Get A “Find” Option There. Use These Options to Get Any Random Questions Answer.

As you already know that this site does not contain only the Linkedin Assessment Answers here, you can also find the solution for other Assessments also. I.e. Fiverr Skills Test answersGoogle Course AnswersCoursera Quiz Answers, and Competitive Programming like CodeChef Problems Solutions, & Leetcode Problems Solutions.

LinkedIn Microsoft Project Skill Assessment Answer

100% Free Updated LinkedIn Microsoft Project Skill Assessment Exam Questions & Answers.

Linkedin Microsoft Project Skill Assessment Details:

  • 15-25 multiple-choice questions
  • 1.5 minutes per question
  • Score in the top 30% to earn a badge
Before you start:

You must complete this assessment in one session — make sure your internet is reliable.
You can retake this assessment once if you don’t earn a badge.
LinkedIn won’t show your results to anyone without your permission.
After completing the exam, you will get the verified LinkedIn Microsoft Project Skill Assessment Badge.

LinkedIn Microsoft Project Skill Assessment Answers

Q1. Where can you set fixed duration, effort driven, and manually scheduled?

  • Team Planner
  • Project Information dialog box
  • task form
  • Resource Sheet

Q2. You would like the ability to edit your typed entries in the Entry Bar, which appears below the ribbon and above the default Entry table in the Gantt Chart view. You recently received a new computer and noticed that the Entry Bar is missing. How do you fix this?

  • Use the Display tab in the Project Options dialog box to enable the Entry Bar.
  • Change the from Gantt Chart view to Tracking Gantt view.
  • Use the Advanced tab in the Project Options dialog box to enable the Entry Bar.
  • On the View tab on the ribbon, in the Split View group, select Details.

Q3. Which of the following defines the project scope in terms of deliverables and components, and provides the framework on which the project status is based?

  • work package
  • work breakdown structure
  • baseline
  • milestone

Q4. When setting the Calculate multiple critical paths option in a master project’s Advanced settings, which statement is correct?

  • Subprojects will have critical paths calculated individually.
  • Individual resources will have critical paths calculated.
  • Milestones will have critical paths fixed.
  • Only one critical path will be calculated for a linked project.

Q5. What Microsoft Project view is shown in the image below?

Microsoft Project Q05
  • Network Diagram
  • Task Dependency Report
  • Flow Chart
  • Gantt Chart

Q6. You want to switch the scheduling mode for a project from scheduling from a start date to scheduling from a finish date. This action will change the default constraint from As Soon As Possible to As Late As Possible. Which dialog box should you use to make this change?

  • Resource Information
  • Project Information
  • Task Information
  • Change Working Time

Q7. A project contains many elements. What is used to describe the sum of the work required?

  • task links
  • Resource Sheet
  • work breakdown structure
  • baseline

Q8. Which option is not available in the Report tab on the ribbon?

  • New Report
  • Network Diagram
  • Recent
  • Custom

Q9. You are troubleshooting a schedule on someone else’s computer The schedule has 10,000 tasks. When a change is made to a task’s duration on a Fixed Units task, the start and finish dates do not change. change highlighting does not appear, and the Gantt Chart bat does not update. What is the cause of this issue?

  • Inserted projects are calculated like summary tasks is selected.
  • Calculate multiple critical paths is not selected.
  • One of the Com add-ins is not selected.
  • Calculate project after each edit is set to Off.

The hint being "The schedule has 10,000 tasks" and the fact that the Gantt Chart does not update.

Q10. You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default?

  • Critical tasks are indicated in red and other tasks are indicated in blue.
  • Critical tasks are indicated in dark blue end other tasks are indicated in light blue.
  • Critical tasks are indicated in a report while the Gantt chart indicates all tasks in blue.
  • Critical tasks are indicated with an icon and other tasks are indicated in blue.

Q11. You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?

  • Must Finish On
  • Start No Earlier Than
  • As Soon As Possible
  • Finish No Earlier Than

Q12. In a project, duration can have different units. Which duration unit is not valid?

  • weeks
  • hours
  • days
  • quarters

Q13. Microsoft Project uses calendars to schedule a project. Which project components can be assigned a calendar?

  • tasks and work
  • work and units
  • resources and work
  • tasks and resources

Q14. You are working on a project file that contains many linked subprojects. When saving the files, what option can you use to immediately save the open files, including those that have not changed?

  • Yes to All
  • Yes
  • Save As
  • Save

Q15. A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?

  • It has changed to 10h.
  • It has changed to 6h.
  • It has changed to 125%.
  • It has changed to 110%.

reference link

Q16. What is another name for a work breakdown structure?

  • a hierarchy of tasks
  • a linking of tasks
  • a duration of tasks
  • a leveling of tasks

Q17. A report for Earned Value Over Time has been requested, You decide to use a Microsoft Project visual report. What values does this report template compare when run?

  • Earned Value. Planned Value, and Actual
  • Earned Value and Planned Value
  • Earned Value and Actual Cost
  • Planned Value and Actual Cost
  • Start-to-Finish (SF)
  • Finish-to-Finish(FF)
  • Finish-to-Start (FS)
  • Start-to-Start (SS)

Reasoning: the problem states that the finish of the secondary dishes should be the same with the finish of the main course. The main course takes longer to complete than the secondary dishes. If we set Start-to-Finish, the secondary dishes will begin after the main dish is complete and this is not what the problem stated.

Q19. A resource is overallocated in a project. This resource is responsible for two tasks that are to happen at the same time. The first of these tasks is on the critical path. Which solution should you use to remedy the overallocation?

  • Use the Leveling Gantt view adjust the edays field for the second task.
  • Use the Task usage view to change the second task contour to an early Peak.
  • Use the Task usage view to change the second task contour to a bell.
  • Use the Leveling Gantt view adjust the edays field for the first task.

Q20. How do you mark a task’s progress and have that progress reflected in the task’s summary task?

  • Use the Task tool on the ribbon’s Task tab for the subtask.
  • Enter a value in the %Complete field.
  • Use the Task tool en the ribbon’s Task tab for the summary task.
  • Use the Project Information dialog box.

Q21. You have many tasks in a project file and want to convert them into milestones. How can you do this?

  • Recreate the tasks and set them as summary tasks.
  • Set the tasks as summary tasks.
  • Unassign any resources from the tasks, as resources are not needed for milestone task.
  • Change the tasks’ duration to 0.

Q22. A project has been delayed by three months. In this project, you have set deadlines that also need to be delayed by three months. What feature should you use to accomplish both of these delays?

  • On the Project tab, click Project Information.
  • On the Task tab, click Move Task.
  • On the Report tab, click Compare Projects.
  • On the Project tab, click Move Project.

Q23. How many default base calendars does Microsoft Project set up for a project?

  • five
  • three
  • two
  • six

Q24. A task has a fixed duration If the units on the task are changed, what value for the task will automatically change as a result?

  • allocation
  • work
  • contour
  • effort

Q25. You are working with subproject files (the master project file is not open) and have saved the changes you made. What happens to the master project when it is opened?

  • The master project will not reflect any changes until the subproject files ate opened as well.
  • The master project will display an error.
  • The master project will display message stating that changes were made and the subproject files must be opened first.
  • The master project will reflect the changes made to the subproject files.

Q26. You need to modify a resource pool. When opening the file that contains the pool, which option is not valid?

  • Open as read-write into d new master project file.
  • Open as read-write and allow others to use the pool.
  • Open as read-only and allow others to use the pool.
  • Open as read-write while locking others from updating the pool.

Q27. On your computer, Automatically add new views, tables. filters. and groups to the global is selected. You are using a custom filter that you created in one of your schedules, and you modify it to better meet your needs. You now notice that this modification is not available in other schedules. How do you fix this?

  • Using More Filters, make a copy of the modified filter.
  • In the Project Options dialog bays clear and reselect Automatically add new views, tables, filters. and groups to the global.
  • Using the Organizer, copy the modified filter from your schedule to global.mpt and replace the filter when prompted.
  • Using Compare Projects, select the appropriate options from the Task Table and Resource Table lists.

Q28. A graduated scale of rates can be created for a resource by using cost rate tables. What is the maximum number of cost rate tables each resource in a project have?

  • five
  • ten
  • six
  • two

Q29. A project currently has a software developer performing two tasks at the same time. The first task is 5 days long; the second task is day long. It has been decided that the developer can take some time to work on the shorter task in the middle the longer task without impacting the schedule. What is the best way to this!

  • Create a link between the tasks with dependency.
  • Change the first task’s contour to Double Peak.
  • Add lag time of -1d to the second task.
  • Split the longer task to accommodate the shorter task.

Q30. You want to change the view of the timescale on Gantt chart to be more granular. How many tiers does the timescale support?

  • three
  • five
  • ten
  • four

Q31. You are assigned the ownership of schedule comprising approximately 12,000 tasks. You need to know exactly, with detail, which tasks have a constraint other than ASAP. The most effective method do this is to create a filter that tests for which set of conditions?

  • Constraint TypeSummaryRecurring% CompleteActive
    1. does not equal As Soon As Possible.
    2. equals Yes.
    3. equals No.
    4. equals 100%.
    5. equals Yes.
  • Constraint TypeSummaryRecurring% CempleteActive
    1. is less than As Soon As Possible.
    2. does not equal Yes.
    3. equals No.
    4. is equal to 0%.
    5. equals Yes.
  • Constraint TypeDetailRecurringDurationActive
    1. is greater than As Soon As Possible.
    2. equals Yes.
    3. equals Yes.
    4. equals 0d.
    5. equals Ongoing.
  • Constraint TypeSummaryRecurring% CompleteActive
    1. does not equal As Soon As Possible.
    2. does not equal Yes.
    3. equals No.
    4. is 1ess than 100%.
    5. equals Yes.

Q32. You are working with two project files. You want the second project to contain some of the same tasks, along with their work assignments, as the first project. You Choose to copy the tasks between the projects. What else is copied along with the task when performing basic copy and paste action?

  • resources
  • baseline
  • calendars
  • work breakdown structure

Q33. You are working with a master project that contains subprojects, and you want to see a list of tasks on which a subproject file is dependent. How can you do this in Microsoft Project?

  • On the Project tab, click Subproject.
  • On the View tab, click Group by.
  • On Project tab. click Links Between Projects.
  • On the View tab, click Filter.

Q34. You want to manage multiple projects with one project designated as the master project. Which button on the ribbon do you use?

  • Subproject
  • Share Resources
  • Move project
  • Link Between Projects

Q35. When you create a new blank project in Microsoft Project, what is the default view?

  • Resource Sheet
  • Task Form
  • Gantt Chart with Timeline
  • Detail Gantt

Q36. A project contains numerous linked tasks. What is the name for a task that is controlled or driven by another task(s)?

  • overlapped
  • predecessor
  • callout
  • successor

Q37. You have several Microsoft Project files open. One contains sensitive information, so you hide that file. What is true regarding the hidden file?

  • The Switch Window lists the hidden file.
  • The Switch Window command does not list the hidden file.
  • To unhide the file, select Switch Window.
  • To view a hidden file, on the View tab, click Arrange Windows.

Q38. In the image below, what does the indicator in Task ID 9 represent?

Microsoft Project Q38
  • subproject
  • linked file
  • custom field
  • resource pool

Q39. You are using work breakdown structure (WBS) codes for an in-progress project. Due to some schedule changes, tasks have been moved around, which has modified the WBS. How do you fix the WBS codes?

  • From the Project tab on the ribbon, click WBS > Define Code.
  • From the Project tab on the ribbon, click WBS > Renumber.
  • From the View tab on ribbon, click Sort.
  • From the View tab on the ribbon, in the Data group, select Group by.
  • Finish-to-Finish (FF)
  • Start-to-Start (SS)
  • Start-to-Finish (SF)
  • Finish-to-Start (FS)

Q41. When breaking down the work that needs to be done on a project, what is the smallest unit of work known as?

  • work package
  • duration
  • work breakdown structure
  • task assignment

Q42. A resource’s hours have increased over the span of five days for a particular task. The duration has not changed, and the task is effort driven. What element can you add to the Task Usage view to see what has changed?

  • Add a column for the actual duration.
  • Add a column for the level assignments.
  • Add a column for the Peak value.
  • Add a column for the assignment.

Q43. You are modifying a project’s work breakdown structure (WBS) code. What is the default length for any selected sequence type?

  • any
  • 5
  • 3
  • 1
  • Start-to-Start (SS)
  • Finish-to-Start (FS)
  • Start-to-Finish (SF)
  • Finish-to-Finish (FF)

Disclaimer:  Hopefully, this article will be useful for you to find all the LinkedIn Microsoft Project Skill Assessment Answer and grab some premium knowledge with less effort. If this article really helped you in any way then make sure to share it with your friends on social media and let them also know about this amazing Skill Assessment Test.  the solution is provided by Chase2learn. This tutorial is only for Educational and Learning purpose.

Please share our posts on social media platforms and also suggest to your friends to Join Our Groups. Don’t forget to subscribe. 

FAQs

What is Linkedin Assessment?

The LinkedIn Skill Assessments feature allows you to demonstrate your knowledge of the skills you’ve added to your profile by completing assessments specific to those skills. LinkedIn skills evaluations are a means to demonstrate the skills of job hunters. This is how LinkedIn Skill Assessments can be used.

Is this Skill Assessment Test is free?

Yes, LinkedIn Microsoft Project Skill Assessment Answer is totally free on LinkedIn for you. The only thing is needed i.e. your dedication toward learning.

When I will get Skill Badge?

Yes, if will Pass the Skill Assessment Test, then you will earn a skill badge that will reflect in your LinkedIn profile. For passing in LinkedIn Skill Assessment, you must score 70% or higher, then only you will get your to skill badge.

How to participate in skill quiz assessment?

It’s good practice to update and tweak your LinkedIn profile every few months. After all, life is dynamic and (I hope) you’re always learning new skills. You will notice a button under the Skills & Endorsements tab within your LinkedIn Profile: ‘Take skill quiz.‘ Upon clicking, you will choose your desired skill test quiz and complete your assessment.

LinkedIn Skill Assessments are a series of multiple-choice exams that allow you to prove the skills that are stated in your profile.

How to get Linkedin Skill Badge?

For getting Linkedin Badge in your profile, you need to score at least 70% and above for getting recognition of skill badges.

If you “grade in the 70th percentile or above”—according to LinkedIn—you officially pass and get a LinkedIn skill badge. The social media site will display your badge on your profile.

How long is Skill Assessment valid for?

Skills assessments that do not specify an expiry date are valid for 3 years from the date of the assessment. If more than 3 years have passed by the time the visa application is made, the skills assessment will no longer be valid.

What is the Benefit of Linkedin Skill Assessment?

  • Chances for getting hired will increased.
  • You will earn Linkedin Skill Badge.
  • Your Linkedin Profile will rank on top.
  • You have a chance to get jobs earlier.
  • This Skill Assessment will enhance your technical skills, helps you to getting recognized by top recruiters, advanced your knowledge by testing your mind.

Who can give this Linkedin Skill Assessment Test?

Any Linkedin User, Any engineer, developer, programmer, who wants to improve their Programming Skills
Anyone interested in improving their whiteboard coding skills
Anyone who wants to become a Software Engineer, SDE, Data Scientist, Machine Learning Engineer, etc.
Any students in college who want to start a career in Data Science
Students who have at least high school knowledge in math and who want to start learning data structures
Any self-taught programmer who missed out on a computer science degree.

How to do linkedin skill assessment

The LinkedIn Skill Assessments feature allows you to demonstrate your knowledge of the skills you’ve added on your profile by completing assessments specific to those skills.

A typical assessment consists of 15 multiple choice questions and each question tests at least one concept or subskill. The questions are timed and must be completed in one session. You can view the full list of available Skill Assessments and sample questions for each.

Available Skill Assessments on LinkedIn

.NET FrameworkAgile Methodologies, Amazon Web Services (AWS), Android, AngularJS, Angular, AutoCAD, AWS, Bash, C, C#, C++, CSS, GIT, Hadoop, HTML, Java, JavaScript, jQuery, JSON, Maven, and MS Vision, QuickBooks, Revit, etc.

What You Need to Know About LinkedIn Skill Assessments

During a job search, wouldn’t it be great to have a way to prove your proficiency in a specific skill to hiring managers?

Well, now there is. On September 17, LinkedIn launched its new Skill Assessments feature. These are online assessments you can take to demonstrate your proficiency in an area such as MS Excel or jQuery. All assessments have been designed by subject matter and LinkedIn Learning experts, and they’re based on an in-depth content creation and review process. Moreover, these assessments seem to be well received: Research shows that job seekers who’ve completed LinkedIn Skill Assessments are approximately 30 percent more likely to get hired than those who haven’t.

How LinkedIn Skill Assessments work
To take an assessment, all you have to do is navigate to the skills section of your profile and select the relevant Skill Assessment. Note that the test is timed. If you have a disability, you can activate the accessibility for the Skill Assessment feature. This will allow you additional time to complete each question.

Your score is private by default, meaning that you can control the visibility of the results. If you score in the 70th percentile or higher, you’ll pass the assessment and have the option of displaying a “verified skill” badge on your profile. If you don’t pass, you can take the assessment again once you’ve brushed up your skills. However, keep in mind that you can only take each assessment once per three months

When you’ve completed an assessment, LinkedIn provides you with an outline of your results. In addition, for a limited time, it offers relevant LinkedIn Learning courses for free so you can improve further. You’ll also receive relevant job recommendations.

According to Andrew Martins in his Business News Daily article “LinkedIn Users Can Now Showcase Skill Assessments,” the following assessments are currently available:

Adobe Acrobat, Angular, AWS, Bash, C, C#, C++, CSS, GIT, Hadoop, HTML, Java, Javascript, jQuery, JSON, Maven, MongoDB, MS Excel, MS PowerPoint, MS Project, MS SharePoint, MS Visio, Node.js, Objective-C, PHP, Python, QuickBooks, Ruby, Ruby on Rails, Scala, Swift, WordPress, and XML. Experts believe that there are also more, non-technical assessments in the making.

A good way to showcase your skills
LinkedIn Skill Assessments offer a brilliant way for you to showcase your abilities to potential employers while at the same time giving you the opportunity to hone your skills even further. So, take advantage of what’s offered — and use it to maximize your employability!

Sources:

https://blog.linkedin.com/2019/september/17/announcing-skill-assessments-to-help-you-showcase-your-skills

https://www.businessnewsdaily.com/15288-linkedin-skill-assessments.html

https://medium.com/alternative-digital-marketing/linkedin-skill-assessments-are-they-worth-it-735867ebe6ae

Tags: linkedin skill assessment,linkedin assessment answers,assessment,linkedin,linkedin skills assessment,linkedin skill assessment answers,linkedin assessment,linkedin microsoft project assessment answers,linkedin microsoft azure skill assessment answers,linkedin excel skill assessment,linkedin assessment quiz answers,linkedin microsoft azure skill assesment answers 2022,linkedin microsoft excel assessment answers,linkedin microsoft azure assessment answers

Leave a Comment